The following projects developed by The Nature
Conservancy and funded by CalFed are scheduled for implementation along the
1. Colusa
protection and restoration activities in Colusa Sub-Reach between River
Miles 144-164.
Cost: $1,488,009
Timeline:
2. Glenn & Butte Counties: Restore 1,218 acres of riparian habitat between
River Miles 178-206.
Cost: $4,950,000.
Timeline:
The following
projects developed by the Nature Conservancy are scheduled for funding.
1. Butte
Big Chico, and Mud Creeks. Acquire fee title, complete baseline
assessments, draft restoration and management plans. Cost: $2,882,945
Timeline: Start at funding and complete three years later.
2. All Counties: Develop and evaluate multi-species conservation flow regime
recommendations. Cost: Unknown Timeline: Start at funding and complete
three years later.